Formwork ( Centering & shuttering work ) is one of
the most common activities in
constructions. Proper measurement of shuttering work is important for accurate billing
and quantity verification.
In this article, we
will understand the Mode of Measurement of Formwork as per IS 1200 (Part-5) including measurement rules, deduction
provisions, and materials used in formwork
What is Formwork ( Centering & Shuttering work )
Formwork is the complete temporary mould system
used to give shape and size as per given drawing to fresh concrete.
It Includes:
Plywood / steel plates
Battens / Studs
Props / Adjustable jacks
Tie Rod / Pin patti
Welding support
Supports & Bracing
and scaffolding as required.
Formwork is a Entire temporary structure used to support and shape, size to
concrete until it gains strength.
Basic rules of formwork measurement
1.
All Dimension measured in square metre
Formwork measured actual surface touch with the concrete or any other material.
Dimensions measured to the nearest 0.01M
Area measured to the nearest 0.01M
No deduction shall be made for opening upto 0.4M².
If slab thickness upto 200MM measure norm
If slab thickness above 200MM measure separately.
Extra Height where exceeding 3.5 metre height in
one floor shall be measured
and paid for separately.
Measurement of Slope area
Sloping
Surface (More than 30°)
If slope is more
than 30°, shuttering may be required on both sides.
But measurement is taken only for the underside area.
Even if shuttering is done on top and bottom, only bottom area is measured.
Arches
Measured separately based on span:
Up to 6 m span
Above 6 m span
Bigger arches are measured separately because they need more support.
If slope is more than 30°, shuttering may be required on both sides.
But measurement is taken only for the underside area.
Even if shuttering is done on top and bottom, only bottom area is measured.
Arches
Measured separately based on span:
Up to 6 m span
Above 6 m span
Bigger arches are measured separately because they need more support.
Cylindrical Shells (Curved Structures)
Only underside area is measured.
Classified by radius:
Radius less than 3 m
Radius more than 3 m
Small curve and large curve are measured separately.
Measurement in stages
Below ground level
Above ground level
Work to be measured separately
work in or under water
work in liquid mode
work in or under foul positions
work in interrupt by tides.
These conditions make execution difficult, so the work is measured separately and usually paid at different rates.
Types of formwork
1. Wrought
formwork :- Planed or smooth timber
surface.
Tongued & grooved board sheathing :- Interlocking wooden boards.
Plywood lined sheathing :- Plywood surface for better finish.
Special lining :- For extra smooth, textured, or architectural finish.
Steel sheeting or tubing :- Steel formwork systems.
Slip form technique :- Continuous extrusion method (used in tall structures
like silos, cores, chimneys).
1 Formwork
Deduction rules
Is 1200 part-5 clause 6
Example
Opening size = 0.35 m²
→ Deduction = No deduction
Opening size = 0.60 m²
→ Deduction = Deduction allowed
|
Shuttering work Deduction Rules |
|||
|
IS 1200 PART-5 |
|||
|
Is 1200 part-5 Clause 6 Mode of measurement |
|||
|
Clause 6.1 shuttering work in
measured in square metres as the
actual surfaces to touch with fresh concrete or any other material |
|||
|
Clause 6.4 No deduction shall be made
for opening upto 0.4M². |
|||
|
Clause 6.5 Ranking or circular
cutting and rounded and moulded edge shall be measured in running metres. |
|||
|
Clause 6.6 Measure secondary beam shuttering only up
to the side of the main beam. Measure main beam shuttering only up to the
side of the column Do not deduct anything from the beam in the main beam. |
|||
|
Deduction Table |
|||
|
Sr. no. |
Opening area |
Deduction Action |
Side addition |
|
1 |
Area upto 0.4 m², |
No deduction |
No Addition |
|
2 |
Area more than 0.4 m² |
Deduct surface area from slab |
add side touch with concrete surface |
|
3 |
Secondary beam measured main beam to main beam |
||
|
4 |
Main Beam measured
no deduction of secondary beam rest area. |
||
|
5 |
If the slab
thickness upto 200MM measured in normally. |
||
|
6 |
If the slab
thickness above 200MM measured separately. |
||
|
7 |
Extra Height where
exceeding 3.5 metre height in one floor shall be measured and paid for separately. |
||
Formwork Design & Tolerance in Constructions
CPWD specification clause 5.2.2
|
Design & Tolerance in Constructions |
|||
|
CPWD Specifications |
|||
|
CPWD Clause 5.2.2 Formwork must be
constructed as per drawing, but small size differences are allowed. |
|||
|
Tolerance Table |
|||
|
S.No |
Item |
Permissible Tolerance |
Simple Meaning |
|
1 |
Columns & Beams (Cross Section) |
+10 mm / -5 mm |
Can be 10 mm bigger or 5 mm smaller |
|
2 |
Footing – Plan Dimensions (L & W) |
+50 mm / -10 mm |
Footing size can slightly vary |
|
3 |
Footing – Eccentricity in Plan |
0.02 × width of footing (Max 50 mm) |
Slight shifting allowed but within
limit |
|
4 |
Footing – Thickness |
+50 mm OR ±5% of thickness (Whichever
is less) |
Thickness variation allowed within
safe limit |
|
|
(Note- These tolerance apply
to concrete dimensions only, and not to positioning of vertical steel or
dowels). |
||
Material for formwork supporting
CPWD specification clause 5.2.3.1
Propping and
Centering
All propping and centering should be either of steel tubes with extension
pieces or built up sections of rolled steel.
Centering & Shuttering work
CPWD specification clause 5.2.3.3shuttering must be strong, properly supported, tight at joints, and clean to prevent leakage and defects. Steel shuttering should generally be used, with waterproof 12MM ply allowed only in small unavoidable areas.
Extra Height support
CPWD specification clause 5.2.3.4
Formwork must be
designed to safely carry its own weight, reinforcement, fresh concrete, and
construction loads (workers, materials, equipment). If the centering height is
more than 3.5 m, multi-stage props should be provided for proper support.
De-shuttering Duration
CPWD specification clause 5.2.3.7
|
De-shuttering work |
|||
|
CPWD Specifications |
|||
|
CPWD Clause 5.2.3.7 Removal formwork
duration |
|||
|
De-shuttering Table |
|||
|
S.No |
Type of Formwork |
OPC 43 Grade |
PPC |
|
1 |
Vertical formwork to columns, walls, |
16-24 Hours |
24-36 Hours |
|
2 |
Soffit formwork to slabs (Props
refixed immediately after removal) |
3 Days |
4 Days |
|
3 |
Soffit formwork to beams (Props
refixed immediately after removal) |
7 Days |
10 Days |
|
4 |
Props to slabs (Span up to 4.5 m) |
7 Days |
10 Days |
|
5 |
Props to slabs (Span over 4.5 m) |
14 Days |
20 Days |
|
6 |
Props to beams & arches (Span up
to 6 m) |
14 Days |
20 Days |
|
7 |
Props to beams & arches (Span
over 6 m) |
21 Days |
30 Days |
Measurement book with example
|
|
PROJECT NAME |
Sun Tower Greater
Noida |
||||||||
|
|
CLIENT NAME |
Onsite XL |
||||||||
|
|
CONTRACTOR NAME |
SANGEETA DEVI |
||||||||
|
|
RUNNING BILL No. |
RA-01 |
||||||||
|
MEASUREMENT BOOK |
||||||||||
|
S.No. |
Description |
Unit |
No. |
No. |
L |
B |
H |
Qty. |
Remarks |
|
|
|
EXAMPLE -1 |
|
|
|
|
|
|
|
|
|
|
|
Footing foundation |
|
|
|
|
|
|
|
|
|
|
|
F-1 ( 3000 X 3000
MM ) Height 450MM |
|
|
|
|
|
|
|
|
|
|
|
Side |
Sqmr |
1 |
2 |
3 |
|
0.45 |
2.7 |
|
|
|
|
Side |
Sqmr |
1 |
2 |
3 |
|
0.45 |
2.7 |
|
|
|
|
Final quantity |
|
|
|
|
|
|
|
5.4 Sqmr |
|
|
|
EXAMPLE -2 |
|
|
|
|
|
|
|
|
|
|
|
column |
|
|
|
|
|
|
|
|
|
|
|
C-1 ( 500 X 750 MM
) Depth 3000MM - 450MM beam |
|
|
|
|
|
|
|
|
|
|
|
side |
Sqmr |
1 |
2 |
0.5 |
|
2.55 |
2.55 |
|
|
|
|
side |
Sqmr |
1 |
2 |
0.75 |
|
2.55 |
3.83 |
|
|
|
|
Final quantity |
|
|
|
|
|
|
|
6.37 Sqmr |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
EXAMPLE -3 |
|
|
|
|
|
|
|
|
|
|
|
Beam |
|
|
|
|
|
|
|
|
|
|
|
B-1 ( 230 X 450 MM
) Lenth 3000MM beam depth 450 - 150 slab thickness = 300 depth of beam side |
|
|
|
|
|
|
|
|
|
|
|
Bottom |
Sqmr |
1 |
1 |
3 |
0.23 |
|
0.69 |
|
|
|
|
2 side both side
same size |
Sqmr |
1 |
2 |
3 |
|
0.3 |
1.80 |
|
|
|
|
Secondary beam
:- measured main beam inner to inner
dimension |
|
|
|
|
|
|
|
|
|
|
|
Final quantity |
|
|
|
|
|
|
|
2.49 Sqmr |
|
|
|
EXAMPLE -4 |
|
|
|
|
|
|
|
|
|
|
|
Beam |
|
|
|
|
|
|
|
|
|
|
|
B-2 ( 300 X 750 MM
) Lenth 3000MM beam depth 750 - 150 slab thickness = 600 depth of beam side |
|
|
|
|
|
|
|
|
|
|
|
Bottom |
Sqmr |
1 |
1 |
3 |
0.3 |
|
0.90 |
|
|
|
|
2 side both side
same size |
Sqmr |
1 |
2 |
3 |
|
0.6 |
3.60 |
|
|
|
|
Main beam :- measured column inner to inner dimension no
deduction from secondary beam area |
|
|
|
|
|
|
|
|
|
|
|
Final quantity |
|
|
|
|
|
|
|
4.5 Sqmr |
|
|
|
EXAMPLE -5 |
|
|
|
|
|
|
|
|
|
|
|
Slab |
|
|
|
|
|
|
|
|
|
|
|
Ceiling |
Sqmr |
1 |
1 |
3 |
|
3 |
9.00 |
|
|
|
|
shaft area 500 X 500MM |
Sqmr |
1 |
1 |
0.5 |
|
0.5 |
|
|
|
|
|
No deduction area
below .4sqmr |
|
|
|
|
|
|
|
|
|
|
|
Final quantity |
|
|
|
|
|
|
|
9 Sqmr |
|
|
|
EXAMPLE -6 |
|
|
|
|
|
|
|
|
|
|
|
Slab |
|
|
|
|
|
|
|
|
|
|
|
Ceiling |
Sqmr |
1 |
1 |
3 |
|
3 |
9.00 |
|
|
|
|
shaft area 800 X 800MM |
Sqmr |
-1 |
1 |
0.8 |
|
0.8 |
-0.64 |
|
|
|
|
shaft side |
Sqmr |
1 |
4 |
0.8 |
|
0.15 |
0.48 |
|
|
|
|
Deduct surface area
but add side of shaft upto slab thickness |
|
|
|
|
|
|
|
|
|
|
|
Final quantity |
|
|
|
|
|
|
|
8.84 Sqmr |
|
|
|
|
|
|
|
Total quantity |
36.61 |
Sqmr |
|||
|
|
|
|
|
|
Previous |
0.00 |
Sqmr |
|||
|
|
|
|
|
|
This Bill |
36.61 |
Sqmr |
|||
Conclusion
Understanding formwork deduction rules as per IS 1200 Part 5 helps engineers measure shuttering work correctly and avoid billing mistakes. Following these standard rules ensures accurate quantity measurement and transparency in construction projects.

0 Comments