Formwork deduction rules is 1200 part 5 shuttering measurement for engineers

Introduction

Formwork  ( Centering & shuttering work ) is one of the  most common activities in constructions. Proper measurement of shuttering work is important for accurate billing and quantity verification.
In this article, we will understand the Mode of Measurement of Formwork as per IS 1200 (Part-5)  including measurement rules, deduction provisions, and materials used in formwork


What is Formwork ( Centering & Shuttering work )

Formwork is the complete temporary mould system used to give shape and size as per given drawing to fresh concrete.

It Includes:
Plywood / steel plates
Battens / Studs
Props / Adjustable jacks
Tie Rod / Pin patti
Welding support
Supports & Bracing
and scaffolding as required.
Formwork is a Entire temporary structure used to support and shape, size to concrete until it gains strength.




Formwork Deduction rules

Basic rules of formwork measurement

1.      All Dimension measured in square metre
Formwork measured actual surface touch with the concrete or any other material.
Dimensions measured to the nearest 0.01M
Area measured to the nearest 0.01M

No deduction shall be made for opening upto 0.4M².
If slab thickness upto 200MM measure norm

If slab thickness above 200MM measure separately.
Extra Height where exceeding 3.5 metre height in one floor shall be measured
and paid for separately.

Measurement  of Slope area


Sloping Surface (More than 30°)

If slope is more than 30°, shuttering may be required on both sides.
But measurement is taken only for the underside area.
Even if shuttering is done on top and bottom, only bottom area is measured.
Arches
Measured separately based on span:
Up to 6 m span
Above 6 m span
Bigger arches are measured separately because they need more support.


If slope is more than 30°, shuttering may be required on both sides.
But measurement is taken only for the underside area.
Even if shuttering is done on top and bottom, only bottom area is measured.

Arches
Measured separately based on span:
Up to 6 m span
Above 6 m span
Bigger arches are measured separately because they need more support.

Cylindrical Shells (Curved Structures)
Only underside area is measured.
Classified by radius:
Radius less than 3 m
Radius more than 3 m
Small curve and large curve are measured separately.


    Measurement in stages

     Below ground level
     Above ground level 


    Work to be measured separately


    work executed under special conditions must be measured separately
    work in or under water
    work in  liquid mode
    work in or under foul positions
    work in interrupt by tides.
    These conditions make execution difficult, so the work is measured separately and usually paid   at           different rates.

  Types of formwork

1.    Wrought formwork :-  Planed or smooth timber surface.
Tongued & grooved board sheathing :- Interlocking wooden boards.
Plywood lined sheathing :- Plywood surface for better finish.
Special lining :- For extra smooth, textured, or architectural finish.
Steel sheeting or tubing :- Steel formwork systems.
Slip form technique :- Continuous extrusion method (used in tall structures like silos, cores, chimneys).


1             Formwork Deduction rules
  Is 1200 part-5 clause 6


       Example
       Opening size = 0.35 m²
→   Deduction = No deduction
       Opening size = 0.60 m²
→   Deduction = Deduction allowed

Shuttering work  Deduction Rules

IS 1200 PART-5

Is 1200 part-5 Clause 6 Mode of measurement

Clause 6.1 shuttering work in measured in square metres  as the actual surfaces to touch with fresh concrete or any other material

Clause 6.4 No deduction shall be made for opening upto 0.4M².

Clause 6.5 Ranking or circular cutting and rounded and moulded edge shall be measured in running metres.

Clause 6.6  Measure secondary beam shuttering only up to the side of the main beam. Measure main beam shuttering only up to the side of the column Do not deduct anything from the beam in the main beam.

Deduction Table

Sr. no.

Opening area

Deduction Action

Side addition

1

Area upto 0.4 m²,

No deduction

No Addition

2

Area more than 0.4 m²

Deduct surface area from slab

add side touch with concrete surface

3

Secondary beam measured  main beam to main beam

4

Main Beam measured no deduction of secondary beam rest area.

5

If the slab thickness upto 200MM measured in normally.

6

If the slab thickness above 200MM measured separately.

7

Extra Height where exceeding 3.5 metre height in one floor shall be measured

and paid for separately.



       Formwork Design & Tolerance in Constructions
 CPWD specification clause 5.2.2


Design & Tolerance in Constructions

CPWD Specifications

CPWD Clause 5.2.2 Formwork must be constructed as per drawing, but small size differences are allowed.

Tolerance Table

S.No

Item

Permissible Tolerance

Simple Meaning

1

Columns & Beams (Cross Section)

+10 mm / -5 mm

Can be 10 mm bigger or 5 mm smaller

2

Footing – Plan Dimensions (L & W)

+50 mm / -10 mm

Footing size can slightly vary

3

Footing – Eccentricity in Plan

0.02 × width of footing (Max 50 mm)

Slight shifting allowed but within limit

4

Footing – Thickness

+50 mm OR ±5% of thickness (Whichever is less)

Thickness variation allowed within safe limit

 

(Note- These tolerance apply to concrete dimensions only, and not to positioning of vertical steel or dowels).


  Material for formwork supporting

      CPWD specification clause 5.2.3.1
Propping and Centering
All propping and centering should be either of steel tubes with extension pieces or built up sections of rolled steel.

     Centering & Shuttering work

CPWD specification clause 5.2.3.3
shuttering must be strong, properly supported, tight at joints, and clean to prevent leakage and defects. Steel shuttering should generally be used, with waterproof 12MM ply allowed only in small unavoidable areas.


      Extra Height support

      CPWD specification clause 5.2.3.4
Formwork must be designed to safely carry its own weight, reinforcement, fresh concrete, and construction loads (workers, materials, equipment). If the centering height is more than 3.5 m, multi-stage props should be provided for proper support.



      De-shuttering Duration

         CPWD specification clause 5.2.3.7

De-shuttering work

CPWD Specifications

CPWD Clause 5.2.3.7 Removal formwork duration

De-shuttering  Table

S.No

Type of Formwork

OPC 43 Grade

PPC

1

Vertical formwork to columns, walls,

16-24 Hours

24-36 Hours

2

Soffit formwork to slabs (Props refixed immediately after removal)

3 Days

4 Days

3

Soffit formwork to beams (Props refixed immediately after removal)

7 Days

10 Days

4

Props to slabs (Span up to 4.5 m)

7 Days

10 Days

5

Props to slabs (Span over 4.5 m)

14 Days

20 Days

6

Props to beams & arches (Span up to 6 m)

14 Days

20 Days

7

Props to beams & arches (Span over 6 m)

21 Days

30 Days



     Measurement book with example


 

PROJECT NAME

Sun Tower Greater Noida

 

CLIENT NAME

Onsite XL

 

CONTRACTOR NAME

SANGEETA DEVI

 

RUNNING BILL No.

RA-01

MEASUREMENT  BOOK

S.No.

Description

Unit

No.

No.

L

B

H

Qty.

Remarks

 

EXAMPLE -1

 

 

 

 

 

 

 

 

 

Footing foundation

 

 

 

 

 

 

 

 

 

F-1 ( 3000 X 3000 MM ) Height 450MM

 

 

 

 

 

 

 

 

 

Side

Sqmr

1

2

3

 

0.45

2.7

 

 

Side

Sqmr

1

2

3

 

0.45

2.7

 

 

Final quantity

 

 

 

 

 

 

 

5.4 Sqmr

 

EXAMPLE -2

 

 

 

 

 

 

 

 

 

column

 

 

 

 

 

 

 

 

 

C-1 ( 500 X 750 MM ) Depth 3000MM - 450MM beam

 

 

 

 

 

 

 

 

 

side

Sqmr

1

2

0.5

 

2.55

2.55

 

 

side

Sqmr

1

2

0.75

 

2.55

3.83

 

 

Final quantity

 

 

 

 

 

 

 

6.37 Sqmr

 

 

 

 

 

 

 

 

 

 

 

EXAMPLE -3

 

 

 

 

 

 

 

 

 

Beam

 

 

 

 

 

 

 

 

 

B-1 ( 230 X 450 MM ) Lenth 3000MM beam depth 450 - 150 slab thickness = 300 depth of beam side

 

 

 

 

 

 

 

 

 

Bottom

Sqmr

1

1

3

0.23

 

0.69

 

 

2 side both side same size

Sqmr

1

2

3

 

0.3

1.80

 

 

Secondary beam :-  measured main beam inner to inner dimension

 

 

 

 

 

 

 

 

 

Final quantity

 

 

 

 

 

 

 

2.49 Sqmr

 

EXAMPLE -4

 

 

 

 

 

 

 

 

 

Beam

 

 

 

 

 

 

 

 

 

B-2 ( 300 X 750 MM ) Lenth 3000MM beam depth 750 - 150 slab thickness = 600 depth of beam side

 

 

 

 

 

 

 

 

 

Bottom

Sqmr

1

1

3

0.3

 

0.90

 

 

2 side both side same size

Sqmr

1

2

3

 

0.6

3.60

 

 

Main beam :-  measured column inner to inner dimension no deduction from secondary beam area

 

 

 

 

 

 

 

 

 

Final quantity

 

 

 

 

 

 

 

4.5 Sqmr

 

EXAMPLE -5

 

 

 

 

 

 

 

 

 

Slab

 

 

 

 

 

 

 

 

 

Ceiling

Sqmr

1

1

3

 

3

9.00

 

 

shaft area  500 X 500MM

Sqmr

1

1

0.5

 

0.5

 

 

 

No deduction area below .4sqmr

 

 

 

 

 

 

 

 

 

Final quantity

 

 

 

 

 

 

 

9 Sqmr

 

EXAMPLE -6

 

 

 

 

 

 

 

 

 

Slab

 

 

 

 

 

 

 

 

 

Ceiling

Sqmr

1

1

3

 

3

9.00

 

 

shaft area  800 X 800MM

Sqmr

-1

1

0.8

 

0.8

-0.64

 

 

shaft side

Sqmr

1

4

0.8

 

0.15

0.48

 

 

Deduct surface area but add side of shaft upto slab thickness

 

 

 

 

 

 

 

 

 

Final quantity

 

 

 

 

 

 

 

8.84 Sqmr

 

 

 

 

 

Total quantity

36.61

Sqmr

 

 

 

 

 

Previous

0.00

Sqmr

 

 

 

 

 

This Bill

36.61

Sqmr

Conclusion 


Understanding formwork deduction rules as per IS 1200 Part 5 helps engineers measure shuttering work correctly and avoid billing mistakes. Following these standard rules ensures accurate quantity measurement and transparency in construction projects.










Post a Comment

0 Comments