This article clearly explains plaster measurement and deduction rules for wall and ceiling plaster work.
These questions are most commonly asked in billing engineer and site engineer interviews.
What is cement plaster work ?
Cement plaster shall be 12MM, 15MM, or 20MM thick as specified in the BOQ item.
Make the surface smooth
Protect the wall
Improve Appearance
Plaster work can be done on
Walls, Ceiling, Columns, Beams.
Plaster deduction Rules clause 3.8 ?
|
Plaster Deduction Rules |
|||
|
Clause 3.8.2 No deduction for Small opening like Exhaust
fan, Duct opening, Ventilator Etc. having area upto 0.5 m², No Deduction is made and plaster is
measured as full wall area. No addition and no deduction. |
|||
|
Deduction for
opening area more than 0.5 m² and upto
3 m², No addition shale made for jambs, sills, soffits etc. When both faces of wall are plaster with
same plaster. Deduction shall be made only one face. If one face of wall are
plaster deduction shall be made 50% of opening area no addition for jambs, sills,
soffits, etc. |
|||
|
In case opening
area above 3 m² each
Full area shall be deduction each side, but jambs, soffits, sills etc.
measured. |
|||
|
Clause 3.8 deductions 1200:1976
part-12 |
|||
|
Sr. no. |
Opening area |
Deduction Action |
Jambs, Soffit,
sills, etc. |
|
1 |
Area upto 0.5 m², |
No deduction |
No Addition |
|
2 |
Area more than 0.5
m² Less than 3 m² |
50% area Deduction
( One face wall ) |
No Addition |
|
3 |
Area Above 3 m², |
Full Area Deduction |
Add Measured |
|
4 |
When the window or
door thickness is parallel to the wall thickness, the wall surface and door,
window surface are on the same line. In this case, no extra plaster is done
on jambs or sill, so no addition is allowed. Full opening deducted each face. |
||
|
5 |
Dimensions shall be measured Nearest 0.01M |
||
|
6 |
Area shall be measured Nearest 0.01 m² |
||
|
7 |
300MM below measured in running metre and above 300MM measured in m². |
||
|
8 |
Clause 3.5 Plastering height greater than 10M above Ground floor shall
be measured separately in stage 5M each story for External plastering work |
||
|
9 |
Clause 3.12 Measurement of wall plaster ( Dimension taken before plastering work ) |
||
Extra height For
plaster work
Now understand carefully
|
Simple Table for Easy Understanding |
|||
|
Sr. no. |
Condition |
How to Measure |
Reference |
|
1 |
Exterior plaster
above 10M Height |
Measure separately
In stages of 5-M |
CPWD specifications
Clause 13.1.9.8 |
|
2 |
Example |
If building height
is 20 meters |
|
|
3 |
Each 5 m height
above 10 m is measured separately |
0 to 10 m → normal
measurement |
|
Cement Consumption for plaster work
|
Description of Item
|
Quantity Per Sqmr |
Remark &
Description of work |
||
|
CEMENT PLASTER (IN
FINE SAND) |
||||
|
(1 : 4) |
5.47 |
547 |
547 KG cement in 100 SQMR plaster for 12MM plaster 1 SQMR
in 5.47KG cement plastering work |
|
|
12 mm plaster: |
(1 : 6) |
3.6 |
360 |
360 KG cement in 100 SQMR plaster for 12MM plaster 1 SQMR
in 3.6KG cement plastering work |
|
15 mm plaster: |
(1 : 4) |
6.54 |
654 |
654 KG cement in 100 SQMR plaster for 15MM plaster 1 SQMR
in 6.54KG cement plastering work |
|
15 mm plaster: |
(1 : 6) |
5.6 |
560 |
560 KG cement in 100 SQMR plaster for 15MM plaster 1 SQMR
in 5.6KG cement plastering work |
|
CEMENT PLASTER WITH
A FLOATING COAT OF NEAT CEMENT |
||||
|
12 mm plaster |
(1 : 3) |
9.54 |
954 |
954 KG cement in 100 SQMR plaster for 12MM plaster 1 SQMR
in 9.54KG cement plastering work |
|
12 mm plaster: |
(1 : 4) |
7.67 |
767 |
767 KG cement in 100 SQMR plaster for 12MM plaster 1 SQMR
in 7.67KG cement plastering work |
|
15 mm plaster: |
(1 : 3) |
10.97 |
1097 |
1097 KG cement in 100 SQMR plaster for 15MM plaster 1 SQMR
in 10.97KG cement plastering work |
|
15 mm plaster: |
(1 : 4) |
8.74 |
874 |
874 KG cement in 100 SQMR plaster for 15MM plaster 1 SQMR
in 8.74KG cement plastering work |
|
CEMENT PLASTER IN
TWO COATS |
||||
|
18 mm cement
plaster in two coats under layer 12 mm thick cement plaster 1:5 finished with
a top layer 6mm thick cement plaster 1:6. |
6.26 |
626 |
626 KG cement in 100 SQMR plaster for 18MM plaster 1 SQMR
in 6.26KG cement plastering work |
|
|
6 MM CEMENT PLASTER |
||||
|
6 mm plaster |
(1 : 3) |
3.67 |
367 |
367 KG cement in 100 SQMR plaster for 6MM plaster 1 SQMR
in 3.67KG cement plastering work |
1. Measurement
book with Example
PROJECT NAME
Sun Tower Greater Noida
CLIENT NAME
Onsite XL
CONTRACTOR NAME
SANGEETA DEVI
RUNNING BILL No.
RA-01
S.No.
Description
Unit
No.
No.
L
B
H
Qty.
Remarks
EXAMPLE -1
Plain Wall
Wall
M²
1
1
5
3
15
Final quantity
15M²
EXAMPLE -2
Wall with small opening upto 0.5M²
Wall
M²
1
1
4
3
12
Ventilator
M²
1
1
0.6
0.6
No Deduction No
Addition
Final quantity
12M²
EXAMPLE -3
Wall with medium opening
0.5M² to 3M²
Wall
M²
1
1
6
3
18
Window
M²
-0.5
1
1.5
1.2
-0.9
Deduct 50% opening area one side wall
No jamb, soffit, Sill addition
Final quantity
17.1M²
EXAMPLE -4
Wall with large opening above 3
M²
Wall
M²
1
1
5
5
25
Door
M²
-1
1
1.5
2.5
-3.8
Deduct the Full opening area each side
add jamb,
M²
2
1
0.23
2.5
1.15
add soffit,
M²
1
1
0.23
1.5
0.35
Final quantity
22.745M²
Total quantity
66.85
Previous
0.00
This Bill
66.85
1. Follow the CPWD Specifications Cement
plaster work
Clause
13.1 Plaster Thickness
Plaster
thickness can be 12MM, 15MM, or 20MM as specified in BOQ item.
Clause 13.1.1 Scaffolding
For all exposed brick work or tile work double
scaffolding independent of the work having two sets of vertical supports shall
be provided. The supports shall be sound and strong, tied together with horizontal
pieces over which scaffolding planks shall be fixed.
Clause 13.1.2 Surface Preparation
Rake joints Properly
Remove Dust, Loose mortar
Wash surface and keep it wet before plaster.
Before start must scaffolding arrangement.
Surface must clean, rough and wet before
start plaster work
Clause 13.1.3 Cement plaster mortar
Ratio Mix as specified in BOQ item.
External plaster under coat Fine aggregate Zone IV
Final Finish coat Fine aggregate Zone V
Most Commonly use Ratio
1:4 (1 cement : 4 fine sand)
1:6 (1 cement : 6 fine sand)
Sand quality changes depending on coat
types.
Clause 13.1.4 application of cement
plaster
Ceiling plaster complete before wall plaster
Plaster start from the top move to downward
Clause
13.1.5 Curing
Curing
should start after
the plaster becomes hard enough so that sprinkling water does not damage or wash it.
The plaster shall be kept wet for a period of at least 7 days.
Mark the executed date on plaster for curing record.
Clause 13.1.8 Precaution for plaster
Before
start plaster check all opening, electric point, wall line , ceiling level etc.
Fixing 150MM wide Chicken wire with U
nail 150 C/C before plastering work on vertical.
Keep wall plaster separate from Ms door frame
plaster by
making a small groove (max 6 mm) while plaster is fresh.
If plaster has cracks, hollow sound, or soft/defective areas, cut that portion in rectangle shape
and redo it.
Clause 13.1.9 Measurement of cement
plaster
Plaster
work measured in Square mater 2 Decimal.
Dimensions shall be measured Nearest 0.01M
Area shall be measured Nearest 0.01 m²
300MM below measured in
running metre and above 300MM measured in m².
Circular work not exceeding 6 m in radius.
Exterior plastering at a height greater than 10 m from average ground level
shall be measured separately in each Story height in stages of 5M height.
Plaster Deduction follow the deduction table.
PROJECT NAME
Sun Tower Greater Noida
CLIENT NAME
Onsite XL
CONTRACTOR NAME
SANGEETA DEVI
RUNNING BILL No.
RA-01
S.No.
Description
Unit
No.
No.
L
B
H
Qty.
Remarks
EXAMPLE -1
Plain Wall
Wall
M²
1
1
5
3
15
Final quantity
15M²
EXAMPLE -2
Wall with small opening upto 0.5M²
Wall
M²
1
1
4
3
12
Ventilator
M²
1
1
0.6
0.6
No Deduction No
Addition
Final quantity
12M²
EXAMPLE -3
Wall with medium opening
0.5M² to 3M²
Wall
M²
1
1
6
3
18
Window
M²
-0.5
1
1.5
1.2
-0.9
Deduct 50% opening area one side wall
No jamb, soffit, Sill addition
Final quantity
17.1M²
EXAMPLE -4
Wall with large opening above 3
M²
Wall
M²
1
1
5
5
25
Door
M²
-1
1
1.5
2.5
-3.8
Deduct the Full opening area each side
add jamb,
M²
2
1
0.23
2.5
1.15
add soffit,
M²
1
1
0.23
1.5
0.35
Final quantity
22.745M²
Total quantity
66.85
Previous
0.00
This Bill
66.85
Clause
13.1 Plaster Thickness
Plaster
thickness can be 12MM, 15MM, or 20MM as specified in BOQ item.
Clause 13.1.1 Scaffolding
For all exposed brick work or tile work double
scaffolding independent of the work having two sets of vertical supports shall
be provided. The supports shall be sound and strong, tied together with horizontal
pieces over which scaffolding planks shall be fixed.
Clause 13.1.2 Surface Preparation
Rake joints ProperlyRemove Dust, Loose mortar
Wash surface and keep it wet before plaster.
Before start must scaffolding arrangement.
Surface must clean, rough and wet before start plaster work
Clause 13.1.3 Cement plaster mortar
Ratio Mix as specified in BOQ item.External plaster under coat Fine aggregate Zone IV
Final Finish coat Fine aggregate Zone V
Most Commonly use Ratio
1:4 (1 cement : 4 fine sand)
1:6 (1 cement : 6 fine sand)
Sand quality changes depending on coat types.
Clause 13.1.4 application of cement plaster
Ceiling plaster complete before wall plasterPlaster start from the top move to downward
Clause 13.1.5 Curing
Curing should start after the plaster becomes hard enough so that sprinkling water does not damage or wash it.The plaster shall be kept wet for a period of at least 7 days.
Mark the executed date on plaster for curing record.
Clause 13.1.8 Precaution for plaster
Before start plaster check all opening, electric point, wall line , ceiling level etc.Fixing 150MM wide Chicken wire with U nail 150 C/C before plastering work on vertical.
Keep wall plaster separate from Ms door frame plaster by making a small groove (max 6 mm) while plaster is fresh.
If plaster has cracks, hollow sound, or soft/defective areas, cut that portion in rectangle shape and redo it.
Clause 13.1.9 Measurement of cement plaster
Plaster work measured in Square mater 2 Decimal.Dimensions shall be measured Nearest 0.01M
Area shall be measured Nearest 0.01 m²
300MM below measured in running metre and above 300MM measured in m².
Circular work not exceeding 6 m in radius.
Exterior plastering at a height greater than 10 m from average ground level shall be measured separately in each Story height in stages of 5M height.
Plaster Deduction follow the deduction table.
Conclusion
Plaster deduction rules are clearly defined as per CPWD specifications.
Small openings are ignored, medium openings get partial deduction, and large openings get full deduction with separate measurement of jambs and soffits.
Understanding these rules is essential for accurate billing and quantity calculation